PennDOT won't talk about the I-80 case while it's in court. But it has said plenty on paper. In a 17-page filing on Nov. 10, the agency asked the state Environmental Hearing Board to turn down the request by Rep. Tarah Probst and Stroud Township resident Lisa Wayland to pause the first phase of construction.

The board hears the case Tuesday and Wednesday, Nov. 17 and 18, in Harrisburg. On Nov. 12, Judge Bernard Labuskes Jr. turned down a request to move the hearing to Stroudsburg. He has not yet decided whether to visit the site.

This is PennDOT's side, as it told the board. The Case Against I-80 runs in a separate article. You can read every filing on the Hearing Board's public docket.

One project, three phases

The full plan rebuilds and widens the 3.5 miles of I-80 between Exits 303 and 307 for about $935 million. It went through one federal environmental review, approved in 2020, but PennDOT is building it in three pieces, west to east. Phase 1 rebuilds Exit 303 in Stroud Township. Phase 2 covers Exits 304 and 305, up to just west of Dreher Avenue. Phase 3 covers Exits 306 and 307, including the closing of the Dreher Avenue exit and the Brodhead Creek bridge. PennDOT said in 2023 that it first planned to do the job in one go, but had to split it up, with each phase starting two to three years after the one before.

That matters here, because the case in front of the board is only about the permits for Phase 1. Much of what opponents object to, including the Dreher Avenue exit, the cemetery, the Fort Hamilton site and Lisa Wayland's home, is in later phases, which will need permits of their own. Opponents argue that the phases should be judged together. On Nov. 10 the judge declined PennDOT's request to throw that argument out, so the opponents will get to make it. He has not decided whether they are right. PennDOT and DEP answer that the permit review already looked at the water impacts of all three phases together.

What this phase actually is

The first phase, which PennDOT calls Section BO1, covers about 1.5 miles of I-80 in Stroud Township, from Shaffer Schoolhouse Road to just west of where the highway crosses Pocono Creek. The contract is worth $232.8 million.

The centerpiece is Exit 303. Today it is a partial exit: drivers heading west can't get off there, drivers heading east can't get on, and there is no direct link to Route 611. PennDOT says that leads to illegal left turns on 611 by drivers leaving the eastbound lanes. The plan rebuilds it as a full "diamond" interchange, with ramps in every direction and a new connector road to North Ninth Street.

The phase also widens the shoulders, lengthens the ramps, and replaces worn-out pavement and bridge parts, including the bridge over White Stone Corner Road.

The safety case

PennDOT's core argument is safety. Its filing says crash rates on this stretch run above the statewide average, with many rear-end crashes, sideswipes and cars hitting fixed objects. The agency blames congestion and a road built to old standards: on-ramps and off-ramps too short to merge safely, shoulders narrower than today's minimum, and aging bridges.

The goal, PennDOT says, is a road that still moves in 2045 without grinding to a halt, brought up to current design standards. Stopping work, it argues, would leave those problems in place, and the board's own rules say a pause should not be granted when public safety is threatened.

Water, wetlands and wildlife

PennDOT's filing says this phase destroys no wetlands and moves no streams. Its list of impacts is short.

The new Exit 303 ramps cross over 0.08 acre of one wetland on a bridge about 67 feet up, with the supports placed to stay out of the wetland. PennDOT says that is high enough to let in light so the plants keep growing. It is still buying 0.16 acre of replacement wetland, twice the area, through a mitigation bank (a business that restores wetlands and sells the credit to builders), and says that will be in place before construction.

About 11 acres of land within 150 feet of protected creeks will be disturbed, much of it already highway. PennDOT says it is planting the same 11 acres of new forest along creeks: just over half an acre on Pocono Creek and about 10.5 acres at a restoration site on McMichael Creek, about 2.5 miles south, chosen with the Monroe County Conservation District.

On flooding, the state Department of Environmental Protection, which issued the permits, backed PennDOT in its own Nov. 13 filing. DEP says an analysis of runoff shows the project will not increase the rate or volume of stormwater leaving the site, and it denies that people living along Arlington Avenue and Bridge Street face greater flood risk. The plan includes stormwater basins, grassy swales and turning some old pavement back into meadow.

On the eagle, PennDOT says the nearest bald eagle nest is about 1.5 miles from this phase. DEP's filing adds a detail: the nest is within 660 feet of the I-80 project in a later phase, which has triggered formal talks with the U.S. Fish and Wildlife Service and the Pennsylvania Game Commission. DEP says PennDOT has started those talks and will continue them as the later phases are designed.

The fort and the homes

PennDOT says Fort Hamilton sits in Stroudsburg Borough, behind Ann Street north of McMichael Creek near Park Avenue, outside this phase. The Pennsylvania Historical and Museum Commission reviewed the archaeology reports and agreed. DEP's filing notes that artifacts PennDOT uncovered were turned over to the commission.

On homes, PennDOT says this phase takes one house, bought by agreement because it already sat partly on state land, plus pieces of three residential properties in Stroud Township. It says Lisa Wayland's home, the old Jimmy's ice cream stand and the gas station next to it are all in the next phase, called BO2, not this one. DEP's filing agrees that any effect on Wayland would likely come from a later phase.

PennDOT also argues that fights over buying land don't belong in front of this board at all. Under state law, the agency says, those disputes go to the county court where the property sits.

Who gets to bring the case

PennDOT argues that Probst has not shown any harm to herself. Citing earlier rulings, it says a state lawmaker cannot go to court on behalf of constituents simply because they live in her district. DEP makes the same point in its filing.

What a pause would cost

PennDOT says stopping work would cost taxpayers real money, since federal tax dollars help pay for the project. In a sworn statement, its top construction official in the district puts delay payments to the contractor, for idle equipment, staging areas, offices and staff, at no less than $300,200 a month. That is about $3.6 million for a one-year pause and $5.4 million for 18 months, based on what PennDOT paid contractors during the 2020 COVID shutdown.

On top of that, the contractor would have to pack up and come back. The contract sets aside $12.8 million to get crews and equipment on site, and PennDOT says it has already paid about $6.4 million of it. Bills would also rise if steel, asphalt or diesel prices climb during a delay, since the contract adjusts for those.

PennDOT also argues there is no rush on the other side. Paving stops for the winter around Oct. 15 and resumes around May 1. Between now and March, it says, the work is mostly putting up temporary barriers, strengthening shoulders so traffic can be shifted next spring, and clearing ground for a stormwater basin that has to be built before the next stage.

What's next

To pause the work, the board has to find that Probst and Wayland are likely to win, that they would suffer harm that can't be undone, and that a pause wouldn't hurt the public more. PennDOT calls a pause "an extraordinary remedy" and says the harm claimed is "nonexistent or highly speculative at best."

PennDOT plans to call its district construction chief, Michael Guidon, and engineers and an environmental planner from its consultant, AECOM. DEP will call its permit reviewers and an engineer from the Monroe County Conservation District. Both agencies say the permits are lawful and the board should let the work go on.

We will cover the hearing.